ExxonMobil’s Prosperity FPSO Achieves Background Flare in 39 Days

January 12, 2024

ExxonMobil’s Prosperity FPSO Achieves Background Flare in 39 Days
(Credit: ExxonMobil Guyana)

ExxonMobil Guyana has unveiled that the Prosperity floating production storage and offloading (FPSO) unit, used in the Payara project, achieved background flare in 39 days, ahead of the 60-day target.

Achieved ahead of schedule outlined in the project’s environmental permit, the accomplishment marks a significant milestone in the company’s commitment to efficient and environmentally responsible offshore operations.

Like the Liza projects, the Payara project design eliminates routine flaring by using produced gas to power the FPSO and reinjecting the rest of the gas into the reservoir to improve oil recovery, thereby reducing emissions.

“Delivering ahead of expectation underscores the value of the lessons learned from our previous projects, which we applied meticulously to Payara’s start-up. We are committed to delivering results that build on our track record of operational excellence,” said Alistair Routledge, ExxonMobil Guyana President.

The Payara project, which began production on November 14, is currently producing more than 180,000 barrels of oil per day.

It is on track to reach its initial production capacity of 220,000 barrels per day during the first quarter, ExxonMobil Guyana said.

Total production from the first three Stabroek block projects is currently over 550,000 barrels per day and expected to reach more than 600,000 barrels per day later this year.

ExxonMobil Guyana operates the Stabroek Block and holds 45% interest. Hess Guyana Exploration holds 30% interest, and CNOOC Petroleum Guyana holds 25% interest.

Fugro Nets Another Offshore Wind Job in Australia

March 10, 2025

Fugro Nets Another Offshore Wind Job in Australia

Shearwater, TotalEnergies Ink Long-Term Marine Seismic Deal

March 5, 2025

Shearwater, TotalEnergies Ink Long-Term Marine Seismic Deal

Abu Dhabi’s TAQA Looks into Cyprus Interconnector Project

February 27, 2025

Abu Dhabi’s TAQA Looks into Cyprus Interconnector Project

Shell Predicts 60% Rise in LNG Demand by 2040 with Asia Leading the Way

February 25, 2025

Shell Predicts 60% Rise in LNG Demand by 2040 with Asia Leading the Way

Cadeler’s Newbuild Offshore Wind Vessel Secures Work in US

February 28, 2025

Cadeler’s Newbuild Offshore Wind Vessel Secures Work in US

PRIO Secures Drilling Permit for Ops at Wahoo Field

March 3, 2025

PRIO Secures Drilling Permit for Ops at Wahoo Field