Tyra II Marks Commissioning Milestone as Ramp Up Activities Gain Ground

February 28, 2025

Tyra II Marks Commissioning Milestone as Ramp Up Activities Gain Ground
Tyra II Development (Credit: TotalEnergies)

TotalEnergies, the operator of the Danish Underground Consortium in charge of the Tyra II development, has achieved a gas export rate above 200 mmscfpd, marking a significant step forward in meeting the requirements to start distribution of gas from the project.

The achieved gas export rate exceeds the threshold of 191 mmscfpd required by the RBL completion test for Tyra.

To satisfy the Tyra Completion Test, gas export must exceed 191 mmscfpd on average over a rolling 30 -day period.

Upon meeting the Tyra Completion Test, BlueNord will reach an important milestone and be able to commence distributions to its shareholders.

Based on current performance and the continued progress of the ramp-up phase, it is anticipated that the 30-day average requirement of 191 mmscfpd will be met in mid-March.

The Danish Underground Consortium, consisting of TotalEnergies, BlueNord and Nordsøfonden, is in charge of the project.

The operator TotalEnergies has announced that the gas production level meets its previously communicated target under REMIT, thereby concluding the REMIT process for Tyra II. 

However, TotalEnergies also announced this morning that they continue to expect the Tyra gas hub to supply up to 2.8 billion cubic meters of gas per year. 

BlueNord said it continues to expect a gross plateau production of approximately 80 mboepd to be reached in March.

The full ramp up of the Denmark’s largest offshore gas development has been delayed several times, due to technical issues impacting the commissioning.

At plateau, the Tyra hub will produce 5.7 million cubic meters of gas and 22,000 barrels of condensate per day once fully commissioned and operational.

The gas from the Tyra hub will be delivered to Europe through two export pipelines to Nybro in Denmark and Den Helder in the Netherlands.


Beacon Offshore’s Shenandoah FPS Reaches US Ahead of Deepwater Installation

February 28, 2025

Beacon Offshore’s Shenandoah FPS Reaches US Ahead of Deepwater Installation

US Congress Overturns Biden’s Methane Fee on Oil and Gas Producers

February 28, 2025

US Congress Overturns Biden’s Methane Fee on Oil and Gas Producers

Cadeler’s Newbuild Offshore Wind Vessel Secures Work in US

February 28, 2025

Cadeler’s Newbuild Offshore Wind Vessel Secures Work in US

Eni to Set Up Carbon Capture Unit as it Looks into Powering Data Centers

February 28, 2025

Eni to Set Up Carbon Capture Unit as it Looks into Powering Data Centers

Tyra II Marks Commissioning Milestone as Ramp Up Activities Gain Ground

February 28, 2025

Tyra II Marks Commissioning Milestone as Ramp Up Activities Gain Ground

Valmet Hooks Methanol Automation Order for Jan de Nul’s CLVs

February 28, 2025

Valmet Hooks Methanol Automation Order for Jan de Nul’s CLVs